Essential maintenance works on the A14 Junction 12 to Junction 13

Our ref: 611598/7 

National Highways Stirling House (Area 7), 

Lakeside Court, Osier Drive, 

Sherwood Business Park, 

Nottingham,

 NG15 0DS 

www.nationalhighways.co.uk 

8th April 2024 

Dear Sir or Madam 

NOTIFICATION OF ESSENTIAL MAINTENANCE WORKS A14 Junction 12 to Junction 13 

I am writing to let you know that we will be carrying out essential maintenance works on the A14 from Junction 12 through to Junction 13.

During our scheme of work, we will carry out;

• Carriageway resurfacing 

• Vegetation clearance 

• Drainage remediation 

• Sign renewal 

When will the work take place? Work is due to start on 22nd April 2024 and is scheduled for completion by end of August 2024. 

Please note that all our planned roadworks may be subject to change due to weather conditions or unforeseen circumstances. 

How will the work affect traffic? To keep our programme for these works as short as possible and to minimise disruption to the local community, residents, businesses and road users, we will be working under full carriageway closures one direction at a time. Closures will be in place between 8pm and 6am, Monday to Friday. Some weekend working may be required and will be advised once programme has been confirmed. During these closures fully signed diversion routes will be in place, which have been agreed with the Local Authority. 

How will the work affect businesses and residents? We will make sure that access to businesses and residences is maintained wherever possible. We apologise for any inconvenience caused and will do our very best to complete the work as quickly as possible, keeping disturbances and noise to a minimum. 

Contact us If you have any questions or if you would like further information about this work, please contact our Public Liaison Officer, as follows: 

• Email: EMcomms@amey.co.uk Alternatively, you can contact our National Highways Customer Contact Centre as follows: 

• Email: info@nationalhighways.co.uk • Telephone: 0300 123 5000 

Yours faithfully, 

Chloe Levenie 

Project Manager National Highways Diversion route for closure of A14 (E) between Junction 12-13 Diversion route for closure of A14 (W) between Junction 13-12 Diversion route for closure of A14 (E) exit slip road